| ID | Indicators | Task Name | Start | Finish | Duration | % Comp. | Resource(s) |
|---|---|---|---|---|---|---|---|
| 1 | Pick up Permits | 04/18/06 | 04/18/06 | 1d | 0 | ||
| 2 | Pre Construction Meeting | 04/19/06 | 04/19/06 | 1d | 0 | ||
| 3 | Start Payment | 04/19/06 | 04/19/06 | 0 | Payment per contract | ||
| 4 | Dumpster Delivery | 04/20/06 | 04/20/06 | 1d | 0 | ||
| 5 | Deck Demo | 04/20/06 | 04/21/06 | 2d | 0 | Creative | |
| 6 | Siding Demo | 04/24/06 | 04/24/06 | 1d | 0 | Creative | |
| 7 | Foundation | 04/25/06 | 04/28/06 | 4d | 0 | Creative | |
| 8 | Framing Lumber Payment | 05/01/06 | 05/01/06 | 0 | Payment per contract | ||
| 9 | Framing | 05/01/06 | 05/11/06 | 9d | 0 | Creative | |
| 10 | Roofing/Siding | 05/08/06 | 05/15/06 | 6d | 0 | Creative | |
| 11 | Install Beam | 05/08/06 | 05/09/06 | 2d | 0 | Creative | |
| 12 | Framing Complete Payment | 05/09/06 | 05/09/06 | 0 | |||
| 13 | Rough Mechanical | 05/15/06 | 05/26/06 | 9d | 0 | ||
| 14 | Electric | 05/15/06 | 05/17/06 | 3d | 0 | Creative | |
| 15 | Plumbing | 05/15/06 | 05/17/06 | 3d | 0 | Creative | |
| 16 | HVAC | 05/15/06 | 05/17/06 | 3d | 0 | Creative | |
| 17 | Rough In Inspection | 05/19/06 | 05/19/06 | 0 | |||
| 18 | Framing Inspection | 05/23/06 | 05/23/06 | 0 | |||
| 19 | Insulation Inspection | 05/26/06 | 05/26/06 | 0 | |||
| 20 | Vandergrift Hood Vent | 05/15/06 | 05/15/06 | 1d | 0 | Creative | |
| 21 | Fireplace | 05/15/06 | 05/16/06 | 1d | 0 | ||
| 22 | Fire Place Install | 05/15/06 | 05/15/06 | 1d | 0 | Creative | |
| 23 | Fire Place Inspection | 05/16/06 | 05/16/06 | 0 | |||
| 24 | Roofing Payment | 05/17/06 | 05/17/06 | 0 | Payment per contract | ||
| 25 | Siding Payment | 05/19/06 | 05/19/06 | 0 | Payment per contract | ||
| 26 | Insulation | 05/25/06 | 05/25/06 | 1d | 0 | ||
| 27 | Drywall | 05/24/06 | 05/31/06 | 6d | 0 | Creative | |
| 28 | Load | 05/24/06 | 05/24/06 | 0.5d | 0 | Creative | |
| 29 | Hang and Finish | 05/25/06 | 05/31/06 | 5d | 0 | Creative | |
| 30 | Drywall Hung Payment | 05/25/06 | 05/25/06 | 0 | Payment per contract | ||
| 31 | Kitchen Demo | 05/08/06 | 05/09/06 | 2d | 0 | Creative | |
| 32 | Tile | 05/25/06 | 06/06/06 | 9d | 0 | ||
| 33 | Floor Heat | 05/25/06 | 05/25/06 | 1d | 0 | Creative | |
| 34 | Sunroom | 06/05/06 | 06/06/06 | 2d | 0 | Creative | |
| 35 | Kitchen | 05/29/06 | 05/30/06 | 2d | 0 | Creative | |
| 36 | Bath | 05/31/06 | 06/01/06 | 2d | 0 | Creative | |
| 37 | 1/2 Tile Install Payment | 06/02/06 | 06/02/06 | 0 | Payment per contract | ||
| 38 | Trim Addition | 06/05/06 | 06/09/06 | 5d | 0 | Creative | |
| 39 | Cabinets | 06/07/06 | 06/16/06 | 8d | 0 | ||
| 40 | Cabinet Delivery | 06/07/06 | 06/07/06 | 0 | Creative | ||
| 41 | Cabinet Delivery Payment | 06/07/06 | 06/07/06 | 0 | Payment per contract | ||
| 42 | Cabinet Install | 06/08/06 | 06/09/06 | 2d | 0 | Creative | |
| 43 | Cabinet Install Payment | 06/09/06 | 06/09/06 | 0 | Payment per contract | ||
| 44 | Painting | 06/08/06 | 06/16/06 | 7d | 0 | Creative | |
| 45 | 1st Coat of Paint Payment | 06/14/06 | 06/14/06 | 0 | Payment per contract | ||
| 46 | Seepage Bed | 06/09/06 | 06/12/06 | 2d | 0 | ||
| 47 | Countertops | 06/12/06 | 06/26/06 | 11d | 0 | ||
| 48 | Template | 06/12/06 | 06/12/06 | 1d | 0 | Creative | |
| 49 | Install | 06/26/06 | 06/26/06 | 1d | 0 | Creative | |
| 50 | Misc Punch & Finishes | 06/19/06 | 06/23/06 | 5d | 0 | Creative | |
| 51 | Finish Mechanicals | 06/19/06 | 06/26/06 | 6d | 0 | ||
| 52 | Plumbing | 06/19/06 | 06/26/06 | 6d | 0 | Creative | |
| 53 | Bath | 06/19/06 | 06/20/06 | 2d | 0 | Creative | |
| 54 | Kitchen | 06/26/06 | 06/26/06 | 1d | 0 | Creative | |
| 55 | Electrical | 06/19/06 | 06/23/06 | 5d | 0 | Creative | |
| 56 | Tile Backsplash | 06/27/06 | 06/28/06 | 2d | 0 | ||
| 57 | Carpet | 06/26/06 | 06/26/06 | 1d | 0 | ||
| 58 | Completion Payment | 06/29/06 | 06/29/06 | 0 | Payment per contract | ||
| 59 | Target Finish Date | 06/30/06 | 06/30/06 | 1d | 0 |